EVH Development Project Working Group

Eardisland Village Hall Development Project Working Group

It’s started! The project finally started on 20 September and now it’s all systems go. Keep your eye on this page for the latest photos every week.

Major problems with rafters on the main hall where the new roof has to join – project temporarily stopped at end of week 4

 

Block work going up nicely by end of week 3.

Footings dug, concrete poured and slab in by end of week 2

   

Going, going, gone! Old kitchen demolished by end of first week

 

 

 

 

 

 

 

 

Before the work started

 

The Group was set in July 2019 to develop the project to update and improve the village hall, following the Feasibility Study undertaken to assess various options and community support for any action.

If you can help the Group with relevant skills, please contact the Parish Clerk and join the Group. Or just come to meetings and give your views in the Open Forum section.

Notes of Meetings

Notes of Project Working Group 23 August 2021

Notes of Project Working Group 16 June 2021

Notes of Project Working Group 7 January 2021

Notes of Project Working Group 30 September 2020

Notes of Project Working Group 11 February 2020

Notes of Project Working Group 7 January 2020

Notes of Project Working Group 25 November 2019

Notes of Project Working Group 22 October 2019

Notes of Project Working Group 11 September 2019

Notes of Project Working Group 10 July 2019

Notes of Project Working Group 4 July 2019

Village hall development project building surveyor specification and scope of works

The relevant documents for tendering for the Work on Eardisland Village Hall can be accessed here:

Tender document for work on Eardisland Village Hall final 
BR07
Ceiling & Wall Insulation Plan-Floor Plans
Door & Window Replacement Plan-Floor Plans
Floor Replacement Plan-Floor Plans
BR02
BR03
BR04
BR05
BR06
Wall, Floor & Ceiling Upgrade Details
17203 Eardisland Village Hall structural condition report PC 04-01-18
Remedial Works to Hall Exterior & Demolition and Re-Build of New Hall Kitchen
Electrical Rewire Specification
Windows & Doors Specification V2

Link to Planning Approval kitchen work 202557 – https://www.herefordshire.gov.uk/info/200142/planning_services/planning_application_search/details?id=202557&search-term=Eardisland%20village%20hall